Click here for instructions on How to Print a Web Page
References: R Record keeping requirement | E An engineering/certification requirement | P A permit to work requirement | S A safe work method statement (SWMS) / written plan
Informative
This section describes MPX approach to hydrostatic and pneumatic pressure testing for building services (hydraulic, fire, mechanical, gas/fuel) pipework and associated systems during installation and commissioning, and highlights potential hazards and risks related to stored energy associated with pneumatic testing. There are many other applications not specifically addressed in this section; however all use pipe work materials as described. MPX requires contactors to review and incorporate the manufacturer’s information and installation guidelines in their safe work methodology.
Hazards
Potential hazards include but are not limited to:
Table 1: Term and Definitions
Informative
Water Supply to Fill a Pipe Work System in Preparation for Hydrostatic Pressure Testing
A Temporary connection from the mains water supply must comply with the water authorities guidelines, for example an acceptable connection incorporates a backflow prevention device in accordance with AS 3500.
A temporary connection from fire hydrant pipe work is allowable provided that prior permission has been obtained from the jurisdictional fire authority and relevant water authority.
In some cases temporary site mains water supply used to fill pipe work systems have been known to harbour large quantities of bacteria which then contaminate filled systems. The water supply is to be sampled to establish a water quality baseline. This will enable the water treatment specialist to effectively and efficiently select the correct water treatment option required for the system.
Pressure Testing
The subcontractor must detail the safety work procedures for pressure testing. The safe work procedure must be submitted to MPX for review.
The type of pressure testing applied to a system may differ due to circumstance: 3 types of typical pressure tests adopted to test pipework systems are described in Table 2.
Different systems required application of either hydrostatic or pneumatic pressure testing or in some cases both, these are described in Table 3.
The test pressure is the pressure to be applied to the system during pressure testing under static conditions. It is typically specified as 1.5 time’s maximum working pressure. The systems working pressure/s and test pressure specifications are normally detailed in the applicable service design documentation.
Pressure testing must not be undertaken until the systems working and test pressures have been defined and are understood by the tester.
The maximum test pressure rating of any system component (E.g. pipework fittings, valves, connections, bellows etc.) should not be exceeded under any circumstances.
THERE IS AN INCREASED RISK ASSOCIATED WITH PNEUMATIC TESTING.
The amount of energy stored in compressed air, is approximately 200 times greater than that contained in water for the equivalent pressure and volume.
If a system component fails during a pneumatic pressure test, there is a high risk of serious injury or damage.
Pneumatic pressure testing should be avoided as far as practical.
In some cases pneumatic integrity testing at low pressures (< 50 kPa) may be considered as a useful means of detecting potential leaks before a full pressure test in conducted.
Pneumatic integrity testing on MPX projects is limited to a maximum pressure of 50 kPa.
Pneumatic pressure testing must be authorised by MPX Site/Services Manager.
Circumstances where pneumatic pressure testing is acceptable are
For the above examples test pressures must be defined in consultation with the system designer.
In cases where:
The testing must be in accordance with applicable:
Sensitive Equipment (energy metres, commissioning sets, etc.)
Where a temporary ‘spool’ piece is installed to protect sensitive equipment, the ‘spool’ piece is to be removed when the hydrostatic pressure test or (where required) the chemical cleaning/disinfection has been completed.
Following the removal of the spool piece, sensitive equipment must be installed with compatible mating flanges / gaskets rated to the specified system working pressure and then hydrostatically pressure tested to the maximum pressure rating of the sensitive equipment in accordance with the manufacturers guidelines.
Plastic Pipes
(Poly vinyl chloride - PVC, polyethylene or cross linked polyethylene - PE, PEX & polybutylene - PB)
In systems compromising of plastic pipes there is likely to be greater expansion of pipe material when pressure or temperature are increased causing any test pressure imposed to decrease over a period of time.
Plastic pipes have specialised jointing techniques which, if faulty or poorly installed will fail.
Acceptable pressure losses must be calculated in accordance with the pipe manufactures guidelines.
Metal Pipe Work Systems
For all metal pipe work systems, a test pressure of at least 1.5 times the maximum working pressure of the system must be applied.
Type of Test and Application
Table 2: Type of Test and Application
Type of System, Test and Notes
Table 3: Type of System, Test and Notes
Hydrostatic Pressure Test
Hydrostatic pressure testing may be carried out when a defined section of a system or when the whole system is completed.
Hydrostatic testing must be only carried out when:
Where a hydrostatic pressure =>2000kPA test is planned authorisation is required to be obtained from MPX Site / Services Manager, in some cases this test maybe required to be undertaken outside of normal work hours and in WA an 'Out of hours' permit is required.
Any leaks that do occur would not cause serious damage to surrounding surfaces.
Hydrostatic pressure testing should be carried out immediately before the commencement of chemical cleaning agent or disinfection, which should be carried out immediately before system commissioning.
The hydrostatic pressure test should be completed within 48 hours to minimise the opportunity for bacteria to develop on pipe surfaces.
Where there is a delay of more than 48 hours between finishing the hydrostatic pressure test and the start of chemical cleaning or disinfection, the system should be left full of biocide dosed water. This controls bacteria levels and prevents the formation of bio film on pipe surfaces.
Hydrostatic pressure testing must be completed prior to any wall / ceiling closures or backfilling of excavation or trench.
NOTE: In some cases it may be necessary to keep sections of the system or individual components isolated and dry whilst other parts of the system are tested. This may be necessary if:
Only those parts of the system that must be tested imminently should be filled. Other parts of the system must be blanked off or isolated. Isolating ball valves with reliable shut off functions should be installed for this purpose.
Prior to Filling the System
Prior to filling the system the installer must:
Filling the System
During the filling of the system, the tester must:
The pump must be attended at all times whilst running
System Test
Once the system is full the system pressure test must commence without delay.
Continue to fill the system with water.
When the system is full of water, the pressure must be increased in staged intervals; the pressure must be raised at intervals in accordance with the pipe manufactures guidelines (to the test pressure and seal the system).
NOTE: Monitoring of the system for leaks should take place continuously throughout all stages of the test.
Monitor the pressure if:
a. the pressure falls the test has failed, check the system for leaks or valves passing
If a successful test is not achieved:
When a successful test is achieved:
Draining the System
Following satisfactory completion of the pressure test, the system should be left charged at a reduced pressure (site mains pressure approx. 250-400 kPa) with water and if required a biocide agent added as specified by water treatment consultant /contractor.
In the event of a full system drain down consideration should be given to the following:
Where biocide dosed water has been used for testing, consideration may be given to leaving this dosed water in the system. The water treatment consultant /contractor must be consulted.
Pneumatic Integrity Test with Air / Inert Gas
Informative
A pneumatic integrity test is required prior to a hydrostatic test to verify there are no open ends or joints which are not welded or crimped prior to filling with water: this is to prevent water damage to surrounding areas.
Pneumatic integrity pressure testing is not permitted to exceed 50 kPa.
NOTE: If the air for the test is to be taken from a source with a pressure higher than 50 kPa, a pressure reducing valve must be set to open if the test pressure (e.g. ≥50 kPa) is exceeded.
During the planning stage for pneumatic integrity testing, system volume should be considered and limited under test to reduce the volume of stored energy of compressed air placed in the system.
The tester is deemed responsible for constantly monitoring the test pressure.
Prior to Testing
The subcontractor must detail the safety work procedures for pneumatic integrity testing. The safe work procedure or SWMS or JSA must be submitted to MPX for review.
Prior to filling the system the installer must:
System Test
The compressor must be monitored at all times to prevent over pressurisation of system.
Increase the air pressure in the system up to the maximum of 50 kPa and seal the system.
Monitor the pressure if:
Draining the System
Once a successful test is achieved, release the air pressure in a deliberate and controlled manner.
Complete or Continue Testing
Where permit was issued for pneumatic integrity test only:
Where authorised and permitted continue with hydrostatic pressure test or pneumatic pressure test in accordance with the relevant sections in ‘Pressure testing pipework’.
Prior to Pneumatic Pressure Test
P Where pneumatic pressure test is planned at a pressure > 50 kPa, authorisation must be obtained from the MPX Services Manager & Site Manager, in some cases pneumatic pressure testing will be required to be completed out of normal work hours and in WA an Out of hours permit is required to be raised.
Access to pneumatic pressure test areas is to be
P WA - Display the Pressure test permit with test rig in the test location.
Tester must verify that the test manifold ‘rig’ is constructed from suitable pressure rated fittings
All relief valves and regulators are isolated (where applicable).
Verify that an adequate number of Competent Persons are readily available to check the system for leaks/failures as the system is filled and, that all the persons involved with the test have been briefed.
The compressor must be attended at all times whilst running.
And in accordance with ‘Pneumatic integrity testing’.
Pneumatic Pressure Test
Only authorised test personnel are permitted within the test area.
The compressor must be attended at all times whilst running.
Monitoring of the system for leaks should take place continuously throughout all stages of the test.
Raise the pressure in staged intervals per the pipe manufactures guidelines, to the test pressure and seal the system.
Monitor the pressure, if:
Do not leave compressor unattended whilst leaks are investigated, the compressor must be monitored to prevent over pressurisation of system.
2. The test pressure remains constant for minimum one (1) hour, the test is deemed successful.
When a successful test is achieved:
Draining the System
Once a successful test is achieved and witnessed, release the air/inert gas pressure in a deliberate and controlled manner.
Document Control
Version 1 August 2019 – New Procedure
Version 2 November 2020 - Procedure applied to VIC and QLD
Version 3 July 2021 - Pneumatic integrity testing on MPX projects reduced to 50 kPa. Where a hydrostatic pressure =>2000kPA test is planned authorisation is required to be obtained from MPX Site / Services Manager.