Façade Panel Launch Tables

References:  R Record keeping requirement | E An engineering/certification requirement | P A permit to work requirement | S A safe work method statement (SWMS) / written plan


Operational


Where used, façade panel launch tables must comply with AS 4100 –Steel Structures and AS/NZS 1554.1: – Structural Steel Welding Part 1: Welding of Steel Structures.


E Proof load test certificates must be supplied (by façade contractor) to MPX prior to use on site.


Façade panel launch tables must be fitted with the following:

  • A compliance plate indicating its maximum capacity.
  • A warning sign (sticker / decal) must be fitted to the launch table alerting the operator to check that the props have been properly deployed prior to use
  • The castors fitted must be of sufficient rated capacity to withstand loads imposed.
  • Façade panel launching tables must be inspected prior to use (castors, pops etc)


Legal and Other Requirements

  • Managing Risks of Plant Code of Practice (Qld) 2013


Document Control       

     

Version 1 August 2019 – New Standard