Click here for instructions on How to Print a Web Page
References: R Record keeping requirement | E An engineering/certification requirement | P A permit to work requirement | S A safe work method statement (SWMS) / written plan
Operational
Earthmoving equipment when used to perform work configured as a crane: must be in accordance with AS 1418.8: Cranes, Hoists and Winches – Part 8: Special Purpose Appliances.
Tracked excavators are permitted to be configured and used as a crane on MPX sites.
Non-tracked earthmoving equipment (e.g. front end loaders, skid steer loaders, excavators on wheels) are not permitted to be configured / used as a crane on MPX sites.
R People carrying out work with earthmoving equipment configured as a crane must be inducted into applicable SWMS and hold valid records of training/competency, evidence must be retained on site refer to:
Where earthmoving equipment is configured and used as a crane:
R Equipment maintenance and inspection records must be maintained in accordance with the manufacturer’s specifications and:
Earthmoving Plant - Lifting Points
Loads are only be suspended from the manufacturer’s designated lift point on the boom or the quick hitch if fitted.
A lifting point should form a closed eye and be arranged so accidental unhooking of the load cannot occur or the sling cannot become detached from the lifting point or load, and such that slings will hang clear of the boom and/or boom attachment.
Legal and Other Requirements
Document Control
Version 1 August 2019 – New Standard